Poncha Meadows 2
Development Updates
Poncha Meadows 2
Breaking Ground
4-15-2025
After 3 years of delays due to a sewer dispute between Salida and Poncha Springs, Poncha Meadows has begun construction on the next phase of their subdivision.
Filing 2, which is approximately 25 acres, will consist of 117 lots, offering both single family and duplex opportunities. Currently, 58 lots are reserved by both the builder community, and individuals.
Y&K Excavation began subdivision construction this week, estimating total completion of Filing 2 in the spring of next year. Lot completions and the ability to pull building permits will be phased through late summer/fall and into next spring. Lots are available from $72,000- $179,000 depending on location, size and number of units allowed.
As Poncha Meadows builds out, the eventual 150 acre development will consist of residential, 15+ acres of commercial amenities along 285, parks and open space, connectivity, and adjacent proximity to the 30+ acre park and recreation land purchased in 2023 by the Town of Poncha Springs.
Carrie Mesch, developer, shared “This has been a haul, getting through long delays and a lawsuit which held up all new Poncha development. We are happy to be moving forward with needed supply solutions to the housing shortage. We have intentionally planned our next phase with product that is more affordable to the valley than other options. Working with the Town of Poncha Springs, we are being very thoughtful and cooperative in creating the culture and vision for our entire development. Phase by phase, we will adjust to market needs. Our goal is to develop an active, attractive, multi-generational, safe, harmonious community.
Thank you to our local team - Piñon Real Estate, Crabtree Group, Henderson Land, Y&K Excavation, and High Country Bank.”

Poncha Meadows 2
On Track for Fall Closings
8-13-2025
Exciting progress! Infrastructure work—including water and sewer—is well underway and right on schedule, paving the way for our first round of closings this fall. A few small lots are still available in Phase 2—secure yours now before prices go up! Check out the pricing sheet and lot availability list to see what’s still open.

Poncha Meadows 2
Continued Progress
9-2-2025
Continued infrastructure work progress—including water and sewer—is moving right on schedule. Only a few small lots remain in Phase 2—secure yours now before prices rise!

Poncha Meadows 2
Nearing Completion for Phase 1 & 2
11-12-2025
Development at Poncha Meadows 2 continues to advance and is now entering the final stages of infrastructure completion.
Last week, we achieved an important milestone with the closing of the first three lots in Block 14.
Site Progress Update:
-
Y&K Excavation is approximately two weeks from full infrastructure completion.
-
Atmos Energy has finalized and signed off on gas utilities.
-
Asphalt paving is scheduled for completion later this week.
-
Sidewalk installation is expected to wrap up next week.
-
Xcel Energy is onsite, fully prepaid, and installation is in progress.
The Developers met with the Town of Poncha Springs last week to discuss final sign-off and lot release timing, which will allow for building permit eligibility. Current projections indicate this will occur by late November.
We will continue to provide updates as the project moves through these final steps. Please reach out with any questions regarding timelines or contract specifics.